Tuesday, May 31, 2016

Tile work is done and the painting has begun

Finally the tile work has been completed and now the glass guy was able to get the measurements for the shower. I guess the delay was due to not all the tile arriving. Not sure I buy that, but they went into overtime to get it completed this last weekend.

This weekend we painted the master bath and put a coat of primer and paint on the doors. But since the doors were raw wood we need at least one more coat. I also painted the eaves since the contractor does not paint. I know it is odd.

I also trimmed the tree that was blocking our view from the bedroom and the deck. I wanted to get it done while we still had the scaffolding.

Today they installed the crown molding and put the vanity in place.

We decided to go with Board by Board to do our flooring. he was recommended by several people on tour nextdoor website. We met with him last week and felt the quote was reasonable. So today the wood for the floors arrived and Jeremy said he will install on June 13th.  If the moisture readings are good he will then sand urethane on June 20th and then we should be able to begin moving the heavy stuff a week later.

Hopefully the end is near and we can finally put our house on the market.












Sunday, May 22, 2016

The tile work has begun

So finally the tiles are going on the wall and floor. For the walls and bench seat we have chosen the classic white subway and for the floors we have chosen a new tile that mimics cement. We wanted to go with a modern feel so the floor tile is a 12x24 and the shower pan is a 4x4 of the same.  For safety reasons we had to go with a smaller tile for the shower otherwise the large tile could make you slip. Our desire was to have a visual effect that the floor was all one type of tile, so when we met with the tile guy we conveyed our layout. Well we stopped by and were not disappointed. So far he has done a very good job. The floor tile grout lines are really small and the grout blends into the tiles.  Once all the subway tile is up the grout will be white and everything should blend nicely together.

One of the problems we are having though is with the wood flooring. Our contractor does not do flooring, which he told us up front. However he said he did have someone who we could get with for a quote as the project got closer to completion.

What we need is to remove the carpet from 2nd bedroom refinish the floor and then feather new flooring to the master bedroom and stain both rooms to match the rest of the house.  We also wanted to get some independent quotes of our own to compare. Well it's not as easy as we thought. I called two companies that were highly on Yelp and neither one called back, so I guess their business must be awesome for them to ignore potential customers.  So we thought that if the contractor's guy's quote was reasonable then we would just go with him.

Today we met at the house for a quote and he showed up with one of his workers. He was probably late 20s and his worker was early 30s but then again I am a very bad judge of age. Anyway, as we were explaining what we wanted I was getting a bad vibe because he just stared and seemed completely lost. Once we were through, he said that all they do is install floors, they do not finish them. That tells me that they just lay floating floors, hell I can do that!! They then said sorry and then beat a hasty retreat.

So today we researched more and I have two bids set for next week, we shall see.








2nd Bath

Wednesday, May 18, 2016

Stucco work done and walls textured

Each day we get a little closer to completion.  The outside was finally stuccoed and the walls are now textured. Sometime this week they should begin the tiling. Once all that is done the only major thing left to do are the floors. This contractor does not do floors (I have no idea why not) but we knew that going into the process.  He has a person that does the work and we will contact them for a quote but we also plan on getting at least one more quote.








Tuesday, May 17, 2016

L.A Trip

This last weekend we needed to get out of San Diego and away from thinking about construction. So we decided on a day trip to LA. It was a long day and you always have to deal with traffic day/night/weekend it does not matter.

towards the end we decided to go to Santa Monica and then we saw THIS. It made the whole trip worthwhile.

Apparently the BatMobile was in the shop because Batman was having to ride a bike.



Construction Creep part 2

Yep we did it again. We have now had them demo the bathroom fixtures and floor to install the tile. I am getting really lazy :(


Thursday, May 12, 2016

Construction Creep

So not much has been happening in the last week. One of the biggest problems with construction or design, is CREEP. As you go along and improve areas you notice other items that could be improved and you think "hey since xxxx is being done I might as well do xxxx too." Well my friend, that is alive and well in this project.  There was a hallway linen closet that was original to the house but did not serve the purpose that we wanted. So we did a dreaded "change order" and decided to have it gutted and turned into a closet. I considered doing it myself later because I did not think it would be that difficult, "but since the construction guys were here........."





Monday, May 2, 2016

Drywall is up

The drywall is now up and should be taped and mudded sometime this week. The contractor said he hopes to have the inspection probably Wednesday.

The blue you see is light filtered through the outside tarp. The do not have the scratch coat or stucco on yet and we had some light rain on Saturday and there is a threat of rain towards the end of this week.